Local News, Marysville City Council, News
August 6, 2025
Two roundabouts on Coleman’s Crossing Boulevard, one at East Fifth Street and one at the western entrance of Walmart, as shown above, will be the first phase of intersection upgrades done on the roadway sometime in the next 1-2 years. Work will also include adding a median, eliminating many of the left turn options for those parking lots. (Graphic submitted)
Roundabout nears completion
Planning for two more begins
The roundabout project at Coleman’s Crossing Boulevard and Industrial Parkway is progressing ahead of schedule and is likely 2-3 weeks from opening.
Kyle Hoyng, engineer at the City of Marysville, said the project was given three months to be completed, putting the opening sometime in mid-September...